Earned Value S Curve, Early vs. Late

10 replies [Last post]
Jose Valdez Marcos
User offline. Last seen 2 years 21 weeks ago. Offline
Joined: 12 May 2001
Posts: 15
Hi all,

I have prepared a WBS earned value report based on all my activity % weighting (Project->WBS). This is working well. Now our client requires an S-Curve between early and late dates. In P3, this is possible, I don’t know in P6. Is there an equivalent resource curve in P6 where I can show these 2 curves (early vs. late dates)?

Regards,

Joe

Replies

Haris Famil Parol
User offline. Last seen 10 years 15 weeks ago. Offline
Joined: 11 Jan 2006
Posts: 12
Groups: None

i am making S cruves for Early and Late loading values extracted from P3.1 and P6 to Excel. If u know the method to generate curve within the P6 with 2 baselines, i would like to know too.

Please send me your steps to harisfamil@gmail.com

Thanks in advance

Regards

 

Haris

vinay M
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 7 May 2009
Posts: 6

Joe,

can you please send me the copy of your S curve prepared on WBS earned value report based on  activity % weighting (Project->WBS) two curves (early vs. late dates)

 

Thanks & regards

V

viny22@yahoo.com

Rex Lorenzo
User offline. Last seen 14 years 36 weeks ago. Offline
Joined: 19 Jun 2009
Posts: 9
Groups: None
Dear all,

A late earned value of progressing program.... Is it useful to use when some of the activies had a negative total float?

As far as project that I involved with we usually use an early and late curve in planning stage wherein the lowest total float is zero. Wish to enhance my knowledge if you could share me how you extract a late data with activities having a negative total float.

Regards,
RL
Jose Valdez Marcos
User offline. Last seen 2 years 21 weeks ago. Offline
Joined: 12 May 2001
Posts: 15
Hi Arnold,

I already received your email with attachment.

Many thanks,

Joe
Shafeeque .
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 25 Mar 2009
Posts: 8
Dear Arnold,

Pls send me too..
shfqp@yahoo.com

Thanks,
Shah
Scarllet Pimpernel
User offline. Last seen 12 years 39 weeks ago. Offline
Joined: 19 Jul 2009
Posts: 152
Dear Arnold,

This is to acknowledge I receive the file.

More power to you.

Many thanks,
Scarlett
Arnold Puy
User offline. Last seen 9 years 8 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Jose,

Already sent.

Jose Valdez Marcos
User offline. Last seen 2 years 21 weeks ago. Offline
Joined: 12 May 2001
Posts: 15
Hi Arnold,

Please send me to my email address:

jose.marcos@macdow.com.au

Thanks in advance,

Joe
Scarllet Pimpernel
User offline. Last seen 12 years 39 weeks ago. Offline
Joined: 19 Jul 2009
Posts: 152
Dear Arnold,

Please send me:

ellenedar@yahoo.com

Many thanks

Scarllet
Arnold Puy
User offline. Last seen 9 years 8 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Jose,

This is possible. Make two copies of your baseline schedule. Then assign it into your current schedule. If you need the steps, forward to me your email.

Regards,

Arnold