How to spread manhour evenly

5 replies [Last post]
mike mark
User offline. Last seen 9 years 46 weeks ago. Offline
Joined: 7 Jul 2009
Posts: 10
Need the steps by step instruction on how to spread manhour evenly on a project in p6 after the project has been progressed several times?

what settting should i set up for this?

how to spread manhours evenly on budgeted unit,actual unit and remaining unit?

Replies

George Ridulme
User offline. Last seen 7 years 13 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 21
Hi Arnold,

My project has a future period bucket data, and i want to update my baseline since i just added a new activity, the problem is I cant update my baseline.

A message box appears indicating that "my project/baseline contains future period bucket data,cant run update baseline against it"

Thanks and Regards,

george
Arnold Puy
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Mike,

Try to use the functionality of Future Period Bucket Planning. This is manually input depending on your forecast man-hour by daily, weekly or monthly.

You can also use the Assign Resource Curve to each activities. However, this will be more better and effective for only those activities takes a longer period.

Regards,

Arnold
Arnold Puy
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi George,

Which version of Primavera you are using? In P6 v7, even there is a future period bucket planning assigned to activities you can still update your baseline schedule.

There is a workaround, prior to updating restore first your baseline schedule and open it. Then, export it and import again and assign as baseline.

Regards,

Arnold
George Ridulme
User offline. Last seen 7 years 13 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 21
Thanks Arnold.

Im using P6, but am not sure what release this version is.

Anyway, thanks again for your help.


Regards,

George
Arnold Puy
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi George,

In order to know which version or release you are using, go to Help --> About Primavera, System Tab.

Regards,

Arnold