EV report

1 reply [Last post]
ROHIT RANGNEKAR
User offline. Last seen 15 years 46 weeks ago. Offline
Joined: 29 May 2009
Posts: 47
Groups: None
Dear All,

I am watching a report by name : “ WBS earned value definition list” in which certain fields are there with values , like EV % completion factor = 4 , EV ETC technique = Total remaining cost and EV performance factor = 0.88 . What these fields stands for and the use of values in them ?

Regards,

Replies

Arnold Puy
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Rohit,

These are the techniques for computing performance % complete & for computing estimate to complete.

Try to change the custom % complete and see what happen. Show the ETC in your column and change the performance factor.

Regards,