Multiple Float path in P6

6 replies [Last post]
Joel Villanueva
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 30 May 2009
Posts: 18
Hi All,

Which Float should I use to calculate multiple float paths by Total Float or Free Float? Which of the two methods is better? Thanks.

Regards,
Joel

Replies

Khuong Do
User offline. Last seen 2 years 3 weeks ago. Offline
Joined: 22 Feb 2010
Posts: 118
Groups: None

Hi,

I also wrote an article regarding use case of this function.

If you're interested, kindly read it here : https://doduykhuong.wordpress.com/2016/01/12/create-critical-path-for-any-activity/

Rafael Davila
User offline. Last seen 9 hours 55 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229
10-4
Joel Villanueva
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 30 May 2009
Posts: 18
Hi Rafael,

Thanks,this is a very informative site understanding logest path & slack calculation.

Regards,
Joel
Rafael Davila
User offline. Last seen 9 hours 55 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229
Whichever in P6 uses Longest Path and Open Ends as critical.

http://scheduleanalyzer.com/sa_long_theory.htm

Best regards
Rafael

Joel Villanueva
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 30 May 2009
Posts: 18
Thank you Arnold, as I understand from your reply, if I will to define my critical path as the longest path free float will be used and Total Float if Critical path is defines by Total Float. Please correct me if I’m wrong?

To All PP’s,

Can anyone please tell me which is the better method that gives better chances of identifying likely causes of delay?

Regards,
Joel
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Joel,

If you will use Total Float then this is used to identify critical paths based on the total float of activity relationships.

While Free Float is used to define critical float paths based on longest path.

It’s up to you which one you will apply.

Regards,

Arnold