calculating multiple float paths

1 reply [Last post]
Somanna Chengappa
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 14 Aug 2013
Posts: 4
Groups: None

I am having a problem with my schedule in calculating multiple float paths

The contractors schedule submitted to me has over 6000 activities this is my first month on this project and I am not very familiar with this schedule. For some reason whenever I try to run the schedule it gets stuck at 95% and then my computer crashes. I think the reason for this is use of multiple calendars and a lot of unnecessary relationships. The schedule in not very good it has random critical paths and the critical path is 80% different from the longest path. 

To get back to my problem, when I asked the contractors scheduler about the problem I have he said to uncheck the option of calculate the multiple float values and run the project I am not sure if it is good idea can anyone explain to me the impacts of this. 

Thanks again 

Regards
Som

Replies

Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

Hi Somanna,

Is there any error message appearing on your screen after your computer crashes? I believe the cause is not because of the huge number of the activities as well as the multiple calendars and unnecessary relationships. And I guess there is nothing to do with the multiple float path.<?xml:namespace prefix = o />

If you mark to calculate multiple critical float paths (sequences of activities) in the project schedule, you can only specify the number of critical float paths.

Cheers,

Arnold