Risk Impact

3 replies [Last post]
Dennis Hanks
User offline. Last seen 9 years 9 weeks ago. Offline
Joined: 17 Apr 2007
Posts: 310
Does anyone have any experience with the Risks feature of P6 (P6.2)?

It may be a useful ’what-if’ tool, if I understood it.

Any constructive thoughts appreciated. Thanks.

Replies

Oliver Melling
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
I think that the risks, issues, thresholds and WPs/Docs functions are all marketing tools.
The idea of having one programme for all project related activity is good, but the functionality of Primavera software is clumsy and too expensive to use for doc control etc.

If you send me your email address i can send you an example PMO risk repor, but i don’t have an excel risk register cos i dont currently use one!
Dennis Hanks
User offline. Last seen 9 years 9 weeks ago. Offline
Joined: 17 Apr 2007
Posts: 310
Oliver;

Thanks for the response - the silence is deafening.

This pretty well confirms my opinion that the "Risks" feature is more for marketing than for use. I put in a couple enhancement requests to make it more date sensitive and hence more useful for ’what-ifs’.

Curious as to how you use it to collate risks. I seldom work at the PMO level, so maybe it is obvious when handling several projects. Any insight appreciated.

Also, if not too great a bother and not violating any ownership issues, any Excel risk register templates that you can share would likewise be appreciated.

Again, thanks.
Oliver Melling
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
Dennis,

I use P5 to collate all risks and issues at PMO level and create high-level reports across divisions as a opposed to just for each project.

There is also a basic impact calculator that will show possible delays or cost overuns that you may be exposed to.

I would say however that the poor response to your thread shows that most people dont use the risk option in Primavera.

If the risk register is in excel then you dont need to P5/6 license to access it it tends to stay more up-to-date!