António Faria
User offline. Last seen 10 years 8 weeks ago. Offline
Joined: 5 Jan 2009
Posts: 40
Groups: None
One question as simple as this:

As default, my projects when created have Standard 5 days working days with basic holidays.

In one particular project, I was trying to change the calendar to Standard calendar.

What I did? Inside Project Workspace, I selected the project and changed the Activity Calendar field in the Bottom Pane/General. Primavera assumes this change, but when I’m in the Activity Workspace, activities still have old calendar. Even pressing "F9", activities don’t assume the Project Calendar Definition.

Best regards,
AF

Replies

António Faria
User offline. Last seen 10 years 8 weeks ago. Offline
Joined: 5 Jan 2009
Posts: 40
Groups: None
Perfect!
Arnold Puy
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Antonio,

In Project Windows --> Default Tab --> Calendar, if you intend to change the calendar it will only intended for the new added activities and not for all existing activities.

In order to change the calendar assigned to the existing activities you need to run the global change or by showing the calendar in the column in activity window, and use the fill down or CTRL+E.