Exporting from P6 to P5

3 replies [Last post]
Blaise Obidegwu
User offline. Last seen 11 years 51 weeks ago. Offline
Joined: 1 Nov 2006
Posts: 8
Hi everybody

I recently exported a project from P6 to P5 and discovered that the total budgeted cost of the project in P5 is less than that of the parent P6 project. Any one knows how this can be remedied?

Regards,
Blaise

Replies

Blaise Obidegwu
User offline. Last seen 11 years 51 weeks ago. Offline
Joined: 1 Nov 2006
Posts: 8
Hi all,

I found out that you will need to use the "Recalculate Cost Assignment" function. That resolved the problem.

Best regards,
Blaise
mike fenton
User offline. Last seen 16 years 20 weeks ago. Offline
Joined: 26 Jun 2008
Posts: 5
Hi,
I had a similiar problem, but discovered that there was a currency misalignment. Each project was setup using a different currency and when importing the "budgeted total cost" would show a different amount.
Dieter Wambach
User offline. Last seen 8 years 9 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Blaise
Do you know which costs are missing, e.g. related to special activities? materials?
Can you find a criterion?
The Xer file is a text-file. You can read it with the Editor or Notepad. Do NOT use Word or any other word processing software because they would add control characters!
Can you find those costs within the file. The record layout is on your documentation cd.

Good luck!