Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Actual Cost Curve not shown

1 reply [Last post]
Jose Valdez Marcos
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 12 May 2001
Posts: 15
Hi everyone,

I am a new P6 user. Why the actual cost cumulative curve not shown in the resource usage profile? Am I missing something here? Appreciate any help from fellow PPs.

Thanks,
Jose

Replies

Arnold Puy
User offline. Last seen 9 years 14 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hello Jose,

Try this. In "Resource Usage Profile Option" --> Data, select the Cost instead of Units then under the Show Bars/Curve, select the "By Date" Actual for Histogram & "Cumulative" Actual for Curve.

HTH.