Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P5 Physical % Complete does not roll up

4 replies [Last post]
Donovan Govender
User offline. Last seen 10 years 4 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 20
Groups: None
What should I do do get physical % complete to roll up in P5
Your help would be appreciated


Donovan

Replies

K D
User offline. Last seen 15 years 29 weeks ago. Offline
Joined: 25 Sep 2007
Posts: 247
Groups: None
I have tested on my PC and it show curve correctly when tick on checkbox of Earned value curve.
You can show "Planned value cost" on activity table to see whether it have value.
K D
User offline. Last seen 15 years 29 weeks ago. Offline
Joined: 25 Sep 2007
Posts: 247
Groups: None
Hi Donovan.
Unfortunately we still have not understood your request.
What window are you currently in to show histogram? Tracking or Activities.

Thanks
Donovan Govender
User offline. Last seen 10 years 4 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 20
Groups: None
Thanks K D ,Really appreciate your help, will try and let you know,I also need to show a histogram with planned, actual & earned and scurves for the same in one profile,
my profile histogram shows my budget,baseline,and actual,but the scurves,I have the planned value labour units & earned value labour units ticked but is not showing,

Please help

Regards
Donovan
K D
User offline. Last seen 15 years 29 weeks ago. Offline
Joined: 25 Sep 2007
Posts: 247
Groups: None
Hi buddy.

’Physical % complete’ is not rolled up, because it is a
discrete, user entered value assigned to an activity. Since
’Physical % Complete’ does not relate to the duration,
units or costs of the activity, there is no common
denominator to use for the summary

Workaround:

It is possible to configure the Activity’s ’Performance %
complete’ to equal the ’Physical % complete’.
Performance % complete can be rolled up to the summary
bands. However, to achieve this, the following three
statements need to be true:
1) The ’% Complete type’ of the activities must be
set to ’Physical % complete’.
2) The ’Technique for calculating performance %
Complete’ needs to be set to Activity % complete.
3) Finally, in order for the Performance %
Complete to be rolled up to the summary band(s),
costs need to be assigned to the activity. These
costs must also be present in the Primary baseline.

This solution derive from Primavera