Resource allocation by week - can it be done??

3 replies [Last post]
Chris Frank
User offline. Last seen 12 years 44 weeks ago. Offline
Joined: 1 Sep 2006
Posts: 11
I’m looking to adjust my resource level on a weekly basis as I will have more men available later in the project is there a way to do thison a single line activity of 8 weeks??

At the moment it allocates the budgeted hours equallly over the duration of the activity.

Replies

Rashid Iqbal
User offline. Last seen 16 years 51 weeks ago. Offline
Joined: 3 May 2005
Posts: 94
Groups: None
Just a note here,

Such kind of a resource allocations are very difficult to handle when it comes to updating. And so if possible divide into different activties and roll them up with an activtiy code.


Regards
Rashid
Chris Frank
User offline. Last seen 12 years 44 weeks ago. Offline
Joined: 1 Sep 2006
Posts: 11
Spot on thanks Peter!!
Peter Holroyd
User offline. Last seen 3 hours 6 sec ago. Offline
Joined: 6 Jun 2005
Posts: 156
you can apply a resource usage curve - front end loaded , back end loaded etc rather than the standard linear. Alternative you can apply the resource more than once to provide a stacked effect

e.g. 2 men * full 8 weeks +
3 men between weeks 3 and 5 +
2 men between weeks 7 & 8

To provide a more accurate allocation