Resource histogram by weeks.

6 replies [Last post]
Dennis Hanks
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 17 Apr 2007
Posts: 310

I'm doing something wrong. I can't get my resource histogram to display by week. It sums to month. Help.

2382
question.jpg

Replies

Dennis Hanks
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 17 Apr 2007
Posts: 310

Tom;

The issue is ordinal dates. The workaround is a small pain - moving back and forth from Timescale Date Format changing in Primary Dates applying, changing again in Primary Dates and re-applying. Apparently the 'bug' has been around since P5. Not a high priority for Larry. Attached is what it should like. Thanks for trying.

2391
question3.jpg

Raymund de Laza
User offline. Last seen 44 weeks 3 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Dennis,

In User Prefrences.. Resource Analysis.. Set Interval into weeks...

 

Regards,

Tom Turnham
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 21 Aug 2013
Posts: 18
Groups: None

Strange. Im affraid I cant help.... When I change the timescale it amends the bars to suit

2390
untitled.png

Dennis Hanks
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 17 Apr 2007
Posts: 310

Tom;

Thanks for the response. Apparently the screen shot is not opening. I'll post again. It should show the timescale set at weeks for schedule and histogram, yet resources are grouped by month. I've sent a Service Request to Oracle - no response. Posting jpg now.

2389
question.jpg

Tom Turnham
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 21 Aug 2013
Posts: 18
Groups: None

Are you just showing it at the buttom of the window using the 'Resource Usage Profile'?

If so just right click in the right hand side of the window and select 'Timescale'. You can then chose the appropriate timescale (Month/Week)

If you are copying it into Excel then go to the 'Assignments' window and do the same (right click in the right window and select 'Timescale')

 

P.S a little courtesy goes a long way.

Tom Turnham
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 21 Aug 2013
Posts: 18
Groups: None