Date Format in P5

3 replies [Last post]
Hady Shendy, PMP
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 11 Jun 2006
Posts: 34
Groups: None
Hi all
Is there any way to display date with the day name
Example:
mon 04-Sep-06
not
04-Sep-06

Replies

David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Hady,

There is no "date to string" functionality in Global change, so it is not possible to combine the user text field with the date field to make it look like MSP.
Hady Shendy, PMP
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 11 Jun 2006
Posts: 34
Groups: None
Thanks david
I insert exatra column before date column, but not looking as in MSP date fromat

I asking again is there any method to attach day of week prior the date itself

Best regards
David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Hady,

Global change has a "day of week" instruction. You will need to use a user text field, e.g. User Text 8 = dayofweek(start)