Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Help needed-Importing MSP to Ver.5

3 replies [Last post]
Suraj Bhatt
User offline. Last seen 9 years 32 weeks ago. Offline
Joined: 24 May 2004
Posts: 58
Groups: None
Hi all!
I am having problem in importing a MSP schedule into Primavera Ver.5.
I have imported the file but as soon as I schedule it in Ver.5 the dates change.Also all the activities that were task dependent in MSP have become resource dependent after importing in Ver.5.
Before importing I selected all the activities and removed "Effort driven". I cleared the baseline too.

Regards,
Suraj

Replies

Marcio Sampaio
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
I understand that it is a default of Primavera - import activities as resource dependent - I never knew a place where I could configure this.
I dont know if it’s diferent in P5, maybe some other PP member could tel us.
By the way it is easy to change this using fill down.

Regards.

Marcio Eduardo
Suraj Bhatt
User offline. Last seen 9 years 32 weeks ago. Offline
Joined: 24 May 2004
Posts: 58
Groups: None
Well thanks!
I solved the dates problem.They match now but why did the activities became resource dependent???
Suraj
Marcio Sampaio
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Suraj Bhatt;

Too many things can be causing this problem.

Calendars, lags, relathionships, durations etc.

I suggest u to check all this topics in all activities and try to find what is wrong.

Good luck.