Hi all!
I am having problem in importing a MSP schedule into Primavera Ver.5.
I have imported the file but as soon as I schedule it in Ver.5 the dates change.Also all the activities that were task dependent in MSP have become resource dependent after importing in Ver.5.
Before importing I selected all the activities and removed "Effort driven". I cleared the baseline too.
Regards,
Suraj