how P3 summarize resource percent complete

5 replies [Last post]
mimoune djouallah
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388

hi dear planners,

how P3 summarize resource percent complete !?

best regards

Replies

mimoune djouallah
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
thanks every body for your reply

best regards
harzelli bouasria
User offline. Last seen 4 years 27 weeks ago. Offline
Joined: 15 Oct 2008
Posts: 42
Hi mimoune
in fact P3 calculate the average of ressources (la moyenne des ressources).

A+
Rodel Marasigan
User offline. Last seen 1 day 2 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Mimoune,
P3 calculate resource percent complete by resource proportion or weightings.
ex:Act1 have 2 resource with diff resource % complete
R1 = 40 units * 20% = 8 unit
R2 = 80 units * 25% = 20 unit
R/C % complete = (8+20)/(40+80) = 23.33% or 23%
mimoune djouallah
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
thanks craig

what i don’t understand is when you show resource percent complete on a column, and you have two resources assigned to one activity, how P3 calculate the percent complete for the two resource together !

best regards
Mimoune
Craig Brough
User offline. Last seen 10 years 42 weeks ago. Offline
Joined: 30 Oct 2002
Posts: 8
Groups: None
Hi

I have not P3 open right now but here is a starter for 10 (or 2):

Group & Sort by resource and set the columns to display % complete.

Or, Export activity data grouped by resource. Export Total budget Quantity, Actual, and remaining and you can derive % Complete from this

Hope this helps.

Craig