Resoucre Workage

1 reply [Last post]
Ross Hatfield
User offline. Last seen 14 years 3 weeks ago. Offline
Joined: 27 Apr 2010
Posts: 3
Groups: None
I need to apply a 75% Workload for certian folks. I have tried the Global Change and that is currently not working. Is there a way this can be done.

Replies

Rodel Marasigan
User offline. Last seen 10 hours 57 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Ross,
Try Global change as shown below and it should work.
P3 Globa Change