Jhorbam Baena Orozco
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None
Hi Fellas...

I have the followin question...how i can make a report that give me the activities that will be execute in the next 48 hours?.

thanks

Replies

Jhorbam Baena Orozco
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None
Shahul Thanks...Thanks...Thanks...
Shah. HB
User offline. Last seen 1 year 27 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
you could check this one out

1. Select option format--> choose filter
2. sample filter named link ahead would be there if not create a new filter using Add option & naming it as per your reference
3. Use the following command
Early dates WR DD+0D DD+2W

DD-Data Date
0D-zero day
2W-two week

4. you could repeat the same for the calender you use i mean in hours you were asking .
Jhorbam Baena Orozco
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None
Shahul...Thanks....but in what of the options of Tabular Reports i’ll find Look ahead?...Can you give me the complete path to find it?...

THANKS A LOT AGAIN
Shah. HB
User offline. Last seen 1 year 27 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
you could prepare look ahead in P3 using tabular report option that would get you what you long for