Storing Period Performance

3 replies [Last post]
Adekunle Arisilejoye
User offline. Last seen 5 years 4 weeks ago. Offline
Joined: 3 Apr 2008
Posts: 52
Could someone explain this statement in more explicit terms pls.

If you store period performance, P3 spreads resource expenditures evenly for each update period and spreads expenditures for the current period from the last close out date to the data date. If yoou do not store period performance, P3 spreads resource expenditures evenly from the resource start through the data date

Replies

Safak Vural
User offline. Last seen 3 years 44 weeks ago. Offline
Joined: 12 May 2008
Posts: 117
Dear Bobo,

If you did not store at every update the situation will be like this:

week 1: 20% progress
week 2: 30% progress
week 4: 40% progress

If you did not store each. When you have a Weekly histogram for resources. Then it will show you.

week 1: 30%
week 2: 30%
week 3: 30%

Regards,

Safak
Adekunle Arisilejoye
User offline. Last seen 5 years 4 weeks ago. Offline
Joined: 3 Apr 2008
Posts: 52
Thanks man.

Cheers