Easy way of changing activity IDs

1 reply [Last post]
yaj sarertnoc
User offline. Last seen 14 years 26 weeks ago. Offline
Joined: 3 Feb 2009
Posts: 5
Groups: None
using global change, i can change the activity ID one at time, is there a fast way of changing the activity id?
ex. activity "A001 - A010" to "B001 - B010"

Replies

Marvin Medina
User offline. Last seen 3 years 46 weeks ago. Offline
Joined: 19 Sep 2008
Posts: 12
yaj,

you can also use the global change when you want to change activity ID’s like what you just did. try to use sample on P3.1.