create project into sub-project

5 replies [Last post]
Ernani Garena
User offline. Last seen 12 years 16 weeks ago. Offline
Joined: 4 Dec 2008
Posts: 36
Can somebody teach me how to copy projects to a new group in P3? I would like to add the two (2) projects I have created to a new project group. Thanks!

Replies

Ernani Garena
User offline. Last seen 12 years 16 weeks ago. Offline
Joined: 4 Dec 2008
Posts: 36
Thanks a lot, it works! But how will it appear under INT4 when under open dialog box? If however I want to open just AR07 or BU09 without opening INT4?
Ernani Garena
User offline. Last seen 12 years 16 weeks ago. Offline
Joined: 4 Dec 2008
Posts: 36
Name Number/Version Title
AR07 Target R07 - Al Rigga Station
BU09 Target R09 - Burjuman Station
INT4 OG Stations Accelerated Program- Rev05
ALQU Target 17-AlQuoz
BUIS Target 16-Business Bay
DUBL Target 26-Dubal

The open project dialog box looks like above. I want to put AR07 and BU09 wihin INT4 in order that AR07 and BU09 will be within INT4 Project. ALQU, BUIS and DUBL were already within INT4 Project. How can I do that? Thank you very much!