Remove Sub-project from Master Project

3 replies [Last post]
Rusydi Usman
User offline. Last seen 18 years 48 weeks ago. Offline
Joined: 3 Feb 2004
Posts: 6
Dear All,
Need your help from ’MSP Master’, I’m using MSP 2003 in creating a Master schedule consist of some sub-projects. I want to remove one of subproject by cutting or deleting the task but it doesn’t work. Can anyone help me how to do this?

regards,
rusydi

Replies

Matthew James
User offline. Last seen 16 years 26 weeks ago. Offline
Joined: 24 Oct 2007
Posts: 4
Groups: None
First post here,

Got just what I needed from this thread. Fixed the issues and working hard again!

Thanks.

Great site!

Matt
Forum Guest
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
Hello,

A very nice person over at PC Productivity Training took the time to offer the following possible solution...

The answer to his question is this:

This is a problem that has been addressed by Microsoft and there is a patch for it that can be downloaded on their website. There is nothing that he is doing wrong, it is on the programming side of Project 2003- the link to the update/hotfix is: http://support.microsoft.com/kb/832887/

I found it when I was looking for my own problem of the Master project overwriting the start dates of the subprojects when they were inserted into the master.

Regards.