Suspending activities in P3

No replies
Ife Olyke
User offline. Last seen 9 years 46 weeks ago. Offline
Joined: 6 Feb 2007
Posts: 147
In P3, I have an activity that has already started and progressed 10% to date. I put a suspend date on the activity for 17th Dec 2008 and resume date for 10th Feb. 2009, but it appears to be suspending the activity from ‘time now’. I was expecting to the activity to be active from time now to 17th Dec, then suspended between 17th dec and 10th feb 09. Anyone experienced this before? Any clues?