Mark Anthony Cortez
User offline. Last seen 15 years 49 weeks ago. Offline
Joined: 9 Apr 2007
Posts: 3
Groups: None
I come across a problem of showing in a bar chart of suspended activity.i have a concrete slab activity and it could not be done continously in my schedule,i have to start and work for a period of 8 days,the stop & resume after 5 days.and continue for another 22 days,this i cant display in the bar chart,i tried it to use suspend date but of no avail.the program is asking for actual start date.please any body can help me?

Thanks a lot,

Mark

Replies

Ife Olyke
User offline. Last seen 9 years 46 weeks ago. Offline
Joined: 6 Feb 2007
Posts: 147
You could have a different calendar id for that activity, where you define the holiday periods. Then go to format => bars => early bars => check box for "neck" and "holidays". Good luck.
Ashraf Jahangeer
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Hi Mark,

It was an interesting excercise however I tried one solution which may suit you.

You can define a seperate calender for the above actvity and show the days as non working for as many days as you like to suspend it.

Regards,

Ashraf