Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

About Progress Override

1 reply [Last post]
efren labay
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 26 Dec 2006
Posts: 12
Hello Again P3 Experts,

Usually the P3 default during running the schedule is by retained logic, I just wanna know when should we use progress override, can someone give me a good/clear example for a vertical construction which almost activities are dependent to one another and for a horizontal construction where activities usually not dependent to each other. Is Progress Override calculation allowed by consultants which they say it will ruin the critical or near critical path of the schedule


Thanks.....

Replies

Ferdinand Fincale...
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 2 Aug 2008
Posts: 140
Hello Efren,

Progress override will indeed neglect the critical and near critical path of the program because when you schedule the program it suggests that the started activity/ies be finished as per the pre-programmed duration without minding the completion of its predecessor activity/ies.

Truly, if there is a lot of project delay, with the retained logic scheduling, your program will always be blown out of its completion period. Nevertheless, it shows the realistic status of the project. Re-scheduling effort is just a pain-in-the-ass on the planner’s part.

Utlizing the progress override scheduling will in a way save a bit of your time in re-scheduling as the program somehow sticks near to its completion period with less duration for adjustment to work on. One thing that I do to go around with the forced advanced completion of activities is that I am changing the predecessor relationship from FS to FF (not of course if it is already FF) and put some +lag if seen to be unrealistic in the program.

Simply sharing.

Ferdinand