SPI & CPI

3 replies [Last post]
Rejo Poothokaran
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 19 Jul 2008
Posts: 8
Hi All,

Could anyone tell me, what is SPI & CPI ?

Replies

Rejo Poothokaran
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 19 Jul 2008
Posts: 8
Thanks to all
Arnold Puy
User offline. Last seen 9 years 13 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi,

SCHEDULE PERFORMANCE INDEX (SPI) – the ratio of work performed (earned value or BCWP) to work scheduled (planned value or BCWS).

COST PERFORMANCE INDEX / INDICATOR (CPI) – the ratio of earned value to actual costs (CPI = BCWP/ACWP). A value greater than 1 indicates that costs are running under budget. A value less than 1 indicates that costs are running over budget. Often used to predict magnitude of a possible cost overrun by dividing it into the original cost estimate (original cost estimate / CPI = projected cost at completion).
Shaneouz Kallal
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 15 Feb 2008
Posts: 6
Hi,
SPI = Schedule performance index
CPI = Cost performance index
Please see details P3 manual or help.

Shaneouz