SPI & CPI in P6 monthwise

2 replies [Last post]
Zil-e-Subhan Malik
User offline. Last seen 10 years 46 weeks ago. Offline
Joined: 22 Feb 2011
Posts: 6
Groups: None

Dear All,

 

WE know that SPI and CPI are calculated by p6 and we only need to open the columns to see the values.

I want to know, is it possible in P6 to have a month wise SPI & CPI from the start of the project to the current date. If it is possible please tell me how?

Regards,

 

Malik

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

what if you grouped by Start then make the Interval Month  ?

Rob O
User offline. Last seen 7 years 2 days ago. Offline
Joined: 27 Aug 2012
Posts: 4
Groups: None

How do I set up a schedule so that it calculates SPI correctly? What % complete types, settings, etc?