SPI/CPI and Project Change

No replies
Kai Chung
User offline. Last seen 7 years 50 weeks ago. Offline
Joined: 6 May 2016
Posts: 2
Groups: None

Hi

I understand how to calculate CPI and SPI and use them in communicating project status. However, can anyone tell me what would happen to these indicators if a project change was raised to alter the scope of delivery, which in turn impacted the time and cost to the project?

Would the project have to be re-baselined? if so, how does this affect the month-on-month comparison of the numbers?

If the project isn't re-baelined, then again, how does this affect the results?

 

Thanks in advance...

Rafael Davila
User offline. Last seen 1 day 55 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

http://www.acq.osd.mil/evm/docs/OTB-OTS%20Guide%20121205.pdf

A lot of tweaking might be necessary if you want to keep old variance.

Be reminded that targeting an outdated baseline is not a good idea.