I understand how to calculate CPI and SPI and use them in communicating project status. However, can anyone tell me what would happen to these indicators if a project change was raised to alter the scope of delivery, which in turn impacted the time and cost to the project?
Would the project have to be re-baselined? if so, how does this affect the month-on-month comparison of the numbers?
If the project isn't re-baelined, then again, how does this affect the results?
Thanks in advance...