Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Total Float Calculations

1 reply [Last post]
Imran Malik
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 24 May 2004
Posts: 20
Groups: None
Dear all
I have no.of projects in one master project. Contractual dates are different for almost every project. While P3 calculates total float for the last project. How can i force p3 to calculate total float for every project when finish date is different for everyone. I tried to apply zero total float for last milestone of the individual project but it made zero and negative for projects finishing earlier. Please help

Replies

Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
You need to add a Finish-no-later-than constraint to the last milestone of each project using that project’s required finish date. Good luck!