Dear all
I have no.of projects in one master project. Contractual dates are different for almost every project. While P3 calculates total float for the last project. How can i force p3 to calculate total float for every project when finish date is different for everyone. I tried to apply zero total float for last milestone of the individual project but it made zero and negative for projects finishing earlier. Please help
I have no.of projects in one master project. Contractual dates are different for almost every project. While P3 calculates total float for the last project. How can i force p3 to calculate total float for every project when finish date is different for everyone. I tried to apply zero total float for last milestone of the individual project but it made zero and negative for projects finishing earlier. Please help