Planned Value and Variance

1 reply [Last post]
moutaz aldeib
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Dear Planners,

In Budget Summary dialog box, the Planned Value is not as the Budget amount, what is the difference?

Another question, in the same dialog box the variance in cost is zero eventhough the earned value and actual to date figures are not the same.

The above example is taken from the project "ENGR" activity "D1070".

Regards,

Moutaz