Activity with Cost But Duration is Dependant in P3

4 replies [Last post]
Benjamin Mora
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 19 Oct 2007
Posts: 66
Groups: None
I have an activity, "Concrete Material Testing", with an associated cost which I want to mirror in terms of duration with "Concrete Paving". In other words, Material Testing should start and end with Concrete Paving. Concrete Paving’s Duration has changed a lot because of the constant design tweaks.

The first idea that came to mind is to use a Hammocks Activity, but I have always thought of Hammocks summative activities and not genuine activities.

Is there something wrong with this approach or is there another or better way? I am working on a very basic schedule, but there are constant revisions.

Thanks.
BEN

Replies

Benjamin Mora
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 19 Oct 2007
Posts: 66
Groups: None
Wonderful...thankyou.
Benjamin Mora
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 19 Oct 2007
Posts: 66
Groups: None
Wonderful...thankyou.
John Raper
User offline. Last seen 8 years 27 weeks ago. Offline
Joined: 17 May 2004
Posts: 44
Groups: None
Ben

Hammocks is the right way to go. You need a S-S from activity to hammock and F-F from hammock to activity. Keep the moving task as an activity and the dependent task as a hammock. Then as one changes the other changes with it.

Using just a F-F and keeping the dependent task as an activity will not adjust its duration, only its finish.
Brad Lord
User offline. Last seen 9 years 47 weeks ago. Offline
Joined: 27 May 2003
Posts: 256
Groups: None
try putting a f-f from concrete paving to concrete material testing