Date format in P3

11 replies [Last post]
A D
User offline. Last seen 4 years 32 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Hi guys,

Normally i use foillowing date format in P3 starting with date followed by month and then year

SAy, 23 JAN 08

One of our client has requested (entire team is Korean) to put in format they work with i.e.

080123 - (Year followed by month and then date)

Is it possible to show in P3?

:)

Rav

Replies

Tommy Nug
User offline. Last seen 6 years 37 weeks ago. Offline
Joined: 16 Nov 2007
Posts: 44
Correct! The problem here is your version differs from what others have. Sometimes, a very simple function can cause a little bit problem when you are a beginner!
A D
User offline. Last seen 4 years 32 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
I hav P3.0,

Just go to Format --> Dates.

U can select the required format.

Cheers,

Rav
Sum Lap Key
User offline. Last seen 17 years 27 weeks ago. Offline
Joined: 8 Nov 2007
Posts: 18
Groups: None
It is P3.0 version. maybe there is no such function.

Thank you very much for your information which is very useful.
Tommy Nug
User offline. Last seen 6 years 37 weeks ago. Offline
Joined: 16 Nov 2007
Posts: 44
What is your version? In p3.1, We dont have the function showed by Nar
Sum Lap Key
User offline. Last seen 17 years 27 weeks ago. Offline
Joined: 8 Nov 2007
Posts: 18
Groups: None
Excuse me, I can’t find the project tab from tools>options in P3.

Can you give me more hints?
Nar Thap
User offline. Last seen 17 years 8 weeks ago. Offline
Joined: 12 Sep 2007
Posts: 73
try this one
tools>option>project tab--- change date format at Dates
cheers
Sum Lap Key
User offline. Last seen 17 years 27 weeks ago. Offline
Joined: 8 Nov 2007
Posts: 18
Groups: None


I mean that when I open P3,Format , then date, I just can choose dates in number format (e.g. 16112007) and I can’t choose the date format like 16Nov2007. Do you know why is that?

Thank you
Tommy Nug
User offline. Last seen 6 years 37 weeks ago. Offline
Joined: 16 Nov 2007
Posts: 44
Hi Sum,
Can you detail more?
Sum Lap Key
User offline. Last seen 17 years 27 weeks ago. Offline
Joined: 8 Nov 2007
Posts: 18
Groups: None
Hi all

I also click* Format>dates. I just select the date format 080123. But I can’t select the date format 23 JAN 08 in my P3 programme. Do you know why?

Thank you


Mercer
A D
User offline. Last seen 4 years 32 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Thanx James,

How Sometime one can forget the basic things and make the problem look worse ?

:-)
James Barnes
User offline. Last seen 2 years 12 weeks ago. Offline
Joined: 6 Sep 2007
Posts: 243
Raviraj

yes, it is possible.

*click* Format>dates

In the dialog box is a selection of date styles. the one you want, I think, is the bottom one

I believe this is view specific so you will need to change it in each of your views

R

James