Hightlight some activities.

3 replies [Last post]
Sundar Singh
User offline. Last seen 11 years 8 weeks ago. Offline
Joined: 20 Sep 2007
Posts: 12
Hi all,
1. I want to highlight some activities with other colours from all activites - there’s any way to do in P3
2. I want cloud some area in Timescale area to show the delay - there’s any way to do in P3.
If somebody know the answer please tell me the steps.

Replies

John Raper
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 17 May 2004
Posts: 44
Groups: None
To cloud out between two dates for the entire programme:
Form the menu choose ’View’; ’Attachment Tools’.
Click on the bottom right tool (two verticals with a squiggle across them).
Click in the bar area and drag to the right.
You now have a shaded area and the dates can be adjusted with the ’handles’ mid way down the screen.

Hope this helps.
Karen Smith
User offline. Last seen 14 years 44 weeks ago. Offline
Joined: 22 May 2007
Posts: 16
Groups: None
Hi Sundar,

You can format the bar of particular activities to change colour and or pattern by selecting the activities then format > selected bars> modify bar format.
Hope this helps.
Karen
Karim Mounir
User offline. Last seen 9 years 37 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi Sundar,

For question #2:
1- U should have a cloud bitmap because P3 doesn’t have any, if u have MS Word then u can find one from the Clip Art (click on Insert-->Clip art and search with keyword: Cloud).
2- Once u got the bitmap from MS Word, copy/paste it in Paint and save it as .bmp (Monochrome Bitmap).
3- Open the schedule in which u want to add the cloud, click on "Insert"-->"Object", 2 windows appear cancel the one titled "Insert Object".
4- Now in the other window (titled "Tools"), click on button showing Triangle, Circle & square (it is used for inserting objects like bitmaps and text).
5- Once pressed, click anywhere in the Gantt Chart area, a window titled "Primavera Symbol Selection" appears, change the "List of File Types" to "Bitmap Files .bmp" and browse to the cloud.bmp which u have saved earlier.’
6- Once selected, it appears in the Gantt Chart, resize it and move to define the activities u want.

That’s all!

Regards,
Karim