How to link schedules?

4 replies [Last post]
Ghassan Zihri
User offline. Last seen 11 years 18 weeks ago. Offline
Joined: 13 May 2006
Posts: 10
Groups: None
Hello planners,

I am using P3.1 and looking to reduce the number of activities in my schedule. Therefore is there is a way to link one schedule to another with one hammock activity only? What are your suggestions/solutions in this regard?

Regards,

Replies

Gün Göksu
User offline. Last seen 11 weeks 14 hours ago. Offline
Joined: 31 Mar 2005
Posts: 123
hello,

"Interproject Relationships" is what you are looking for.

password: INTRPROJ

it is located under:

P3PROGS\INTRPROJ.EXE

please read the related help files BEFORE doing any changes.
Always write the changes down, link between milestones clearly defined as "linked/from". If you don’t do this, after some time, you will forget they are there and wonder (possibly spending hours in the process) why the schedule is acting weird.

hope this helps.

Gün :)
Ghassan Zihri
User offline. Last seen 11 years 18 weeks ago. Offline
Joined: 13 May 2006
Posts: 10
Groups: None
Hi,

thank you for your reply. I want to create a hammock activity in one program then to link this activity to an external program. My purpose is to reduce the number of activities of the program that I submit to the Engineer Representative. "Interproject" offers the option to link 2 programs with a FS link. I will keep trying and let you know.

Regards,
Karen Smith
User offline. Last seen 16 years 11 weeks ago. Offline
Joined: 22 May 2007
Posts: 16
Groups: None
Hi Ghassan,
Do you mean reduce the number of activities by linking to your other schedules and thus reducing repetition?
If so can your other schedules be sub-projects and then link with milestones, I haven’t used/considered a hammock but the milestones work well.
Cheers.
Karen
Brennan Westworth
User offline. Last seen 8 years 19 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
If they are sub-projects of the same project group this isnt a problem.

I have never tried to use interproj for hammocks, but i imagine it wouldnt work.