Actual activity drives its succcessor

3 replies [Last post]
OSMAN CERAN
User offline. Last seen 12 years 22 weeks ago. Offline
Joined: 22 Mar 2007
Posts: 4
Groups: None
Dear Friends

I come across with a problem resulting from driving activities.

The activities that have actual start and finish dates drice their successor activities since their predecessors are not actual.

Let me explain wit a simple example

C200 Construction / P200 Procurement Phase-2 / P100 Procurement Phase-1

P200 drives its successor C200 altough P200 has actual start and finish dates. However P200’s predecessor P100 is not actual.

Your advice regarding the issue will be highly appreciated.

Thanks

Osman

Replies

David Moses
User offline. Last seen 11 years 24 weeks ago. Offline
Joined: 20 Oct 2004
Posts: 122
Hi There,

On your case,

If you run the schedule, you will see some messages like,

a) Activity started, predecessor has not finished.
b) Activity started too early to allow it to finish after the expiration of its predecessor’s lag.

etc. etc... on the Scheduling Report Page.

That means there are some relationship problems on your current schedule.

Solution:
1) Ignore it
2) If your client accepts, change those activities relationship logic.

Regards,
OSMAN CERAN
User offline. Last seen 12 years 22 weeks ago. Offline
Joined: 22 Mar 2007
Posts: 4
Groups: None
Rey

Thank you very much!

Osman
Rey Basadre
User offline. Last seen 15 years 49 weeks ago. Offline
Joined: 5 Mar 2006
Posts: 24
Osman,

Re-schedule and/or modify the link between those activities to reflect the current status/situation, or use Progress Override option.

Rey