Is the activity resource-driving if it is leveled?

2 replies [Last post]
Sum Lap Key
User offline. Last seen 17 years 28 weeks ago. Offline
Joined: 8 Nov 2007
Posts: 18
Groups: None
Is the activity resource-driving if the activity is required to be leveled?

Replies

Mohamed Basheer
User offline. Last seen 6 years 40 weeks ago. Offline
Joined: 1 Apr 2004
Posts: 22
Groups: None
Hi sum and Mike

First of all leveling is done when one or more resource is excessively required but not continuously. I think we have to make resource driven / specify available limits so that P3 can reschedule the non critical activities within the allowable lag respecting their relationship.

Hope my understanding is right though I have not practically done it.
Mike Morrison
User offline. Last seen 17 years 30 weeks ago. Offline
Joined: 25 Jul 2007
Posts: 14
Groups: None
Im not an expert with resource leveling. I think you are referring to whether the "driving" checkbox in the "cost tab" must be selected if you want to level the resources for the schedule, including the ones in that activity.

Can somebody provide a little more focus on this? Or am I overcomplicating the question?