1 reply [Last post]
Terry White
User offline. Last seen 13 years 15 weeks ago. Offline
Joined: 8 Feb 2004
Posts: 39
Groups: None
How do I format the Gannt chart so that there is a logical flow of the bars in order of sequence of works ? I’m finding that I’m having to change the Activity Id so that tasks fall into a logical sequence.

Replies

Rodel Marasigan
User offline. Last seen 8 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Terry,

Select Format-> Organise or click Organise icon. Under Sort by: change sort on column to Early Start and order to Ascend then click Organise now.

Rodel