Sheduling - Loop

4 replies [Last post]
J Venkatesh PMP P...
User offline. Last seen 12 years 6 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
Hi...

Am using P3.1 and I have liknked all the activities in a project and when I was scheduling (Pressing F9), got a report as schedule termiated..loop detected...

since there are lot of activities, i cudnt able to find the link defect of particular activity...

can anyone suggest, how to find / generate a report showing the defect link / activty..

rgds
venkat

Replies

J Venkatesh PMP P...
User offline. Last seen 12 years 6 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
Dear Honnes,

its worked well...

thx
Hannes de Bruyne
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 25 Jul 2005
Posts: 154
Groups: None
Hello Jaya

Don’t use F9 for scheduling, use the Icon with the red clock.

This will give you the report

Hannes
J Venkatesh PMP P...
User offline. Last seen 12 years 6 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
Dear Ramana,

thanks for ur immediate response...

but when am scheduling it, am not getting detailed report, just its showing scheduling terminated and loops detected...

I don kno, whther any installation file wud be missing????
VENKAT RAMANA
User offline. Last seen 15 years 9 weeks ago. Offline
Joined: 8 Feb 2007
Posts: 25
Heyy...

After scheduling i think you got a report of the loops detected...Actually loops are traced when activities are linked incorrect..i.e example of a loop is A-B-C-D-A..just go to the activity A and check its predecessor or successor and make correction..ur schedule shall be successful.

Regards,
VENKAT RAMANA