Hi...
Am using P3.1 and I have liknked all the activities in a project and when I was scheduling (Pressing F9), got a report as schedule termiated..loop detected...
since there are lot of activities, i cudnt able to find the link defect of particular activity...
can anyone suggest, how to find / generate a report showing the defect link / activty..
rgds
venkat
Am using P3.1 and I have liknked all the activities in a project and when I was scheduling (Pressing F9), got a report as schedule termiated..loop detected...
since there are lot of activities, i cudnt able to find the link defect of particular activity...
can anyone suggest, how to find / generate a report showing the defect link / activty..
rgds
venkat