how can i adjust project target duration?

3 replies [Last post]
ELSON JOHN SANTOS
User offline. Last seen 18 years 2 weeks ago. Offline
Joined: 26 Nov 2006
Posts: 3
Groups: GPC Qatar

Replies

Jason Smith
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 11 Dec 2006
Posts: 4
Groups: None
If you choose to use the update target feature I would save a back up first. Make sure that you choose only the items that you want to have updated on the target file. It is easy to update more than you wanted to if you are not careful.
Eric EVRARD
User offline. Last seen 7 years 38 weeks ago. Offline
Joined: 4 Dec 2006
Posts: 25
Groups: None
Hello,
A project target is only another project recorded in your P3 files and then shown on your layout when selected.
You need to open the project you use as a target, change whatever you want and it will appear with its modifications on the project you use.
Alex Wong
User offline. Last seen 12 years 21 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
read the tutorial of how to create a schedule... that will help