PROJECT SCHEDULE DURATION

6 replies [Last post]
Weni Samson
User offline. Last seen 18 years 24 weeks ago. Offline
Joined: 18 Nov 2006
Posts: 18
Groups: None
Could someone tell me how many days or months it would take to do a complete project schedule (from scratch to finish) of a 3 Basement + 50 Floors building of a person having an average experience on planning & scheduling using P3? Thanks a lot.

Replies

Santhosh kumar Na...
User offline. Last seen 7 years 26 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 66
Hi,
I clearly mentioned that it depends the level of details. But to find project completion date 20 days is ok..

You can develop activities like rafts in in 10 0r 15 zones, detailed vertcals & horizonatl of a typical floor and mutliply the duratioon eith combination of floors... core wall duration for atypical floor ,one or 2 activities for evelvators , 5- 6 actvities for external cladding and typical floor finsh will do the purpose... it will not more than 20 days.....
Cost loading , resources, loading etc... ofcourse will take time... full programm approval will take 6 month or more with many revisions....


thanks
ruben quintal
User offline. Last seen 17 years 27 weeks ago. Offline
Joined: 26 Sep 2006
Posts: 33
Groups: None
weni,

if ur new to the trade, try to make a draft schedule as fast as you can (within one week or less).then present these schedule to the responsible persons(CM,PM,PIC,etc.).they will surely be giving a lot of comments and it will now be easier for you to take it from there. this will make the planning duration a little shorter.
Alex Wong
User offline. Last seen 12 years 13 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
And of course the complexity of the project

But bare min. is 20 working days

Alex
David Andreotti
User offline. Last seen 9 years 16 weeks ago. Offline
Joined: 6 Jul 2005
Posts: 47
Groups: None
Weni;

It could take even longer depending upon which team players are available to you. A superintendent would be required to really be effective. A good strong knowledge of the construction drawings is req’d. Are u cost loading/resource loading the sched? What about enigneering and procurement tasks. A lot depends on most of these issues.

Good Luck.
Weni Samson
User offline. Last seen 18 years 24 weeks ago. Offline
Joined: 18 Nov 2006
Posts: 18
Groups: None
Thanks. That could be of help.
Santhosh kumar Na...
User offline. Last seen 7 years 26 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 66
Hi,
It depends which level of detailing you need!! emm mostly to arrive the durtaion of the project with minimum detailing you may reqiure 15 to 2o days