resource levelling

3 replies [Last post]
John Moss
User offline. Last seen 14 years 3 weeks ago. Offline
Joined: 3 Feb 2004
Posts: 4
Groups: None
Hi

I am trying to resource level and have assigned a max and normal limit to a driving resource. I want a max limit greater than 9999, but P3 does not seem to allow an input greater than 4 digits long. Anyone had this problem ?

Thanks

John

Replies

John Raper
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 17 May 2004
Posts: 44
Groups: None
John

Have you tried dividing by 8 or 40, and showing the time window in days or weeks?

Hope this helps
John R
Paul Harris
User offline. Last seen 2 years 13 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
There are a couples place in P3 where there is a 9999 limit including activity duraton which restricts the total duration of a project.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
David Kelly
User offline. Last seen 2 years 46 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
John,

I’ve always just divided the resource requirement and the resource availablity by a factor of 10.