levelling of resources

3 replies [Last post]
sunil kumar
User offline. Last seen 15 years 40 weeks ago. Offline
Joined: 18 Oct 2005
Posts: 47
Groups: None
once i do levelling of a particular resource... and scheduling it will again come to where i started... how can i retain the schedule as it is( i mean levelled schedule)

Replies

Christian Adrian ...
User offline. Last seen 6 years 6 weeks ago. Offline
Joined: 3 Jun 2003
Posts: 193
Groups: None
Hello,

If your not satisfied with automatic levelling perhaps you could also do the manual levelling before you try to schedule it... but make sure you back-up your copy first before doing any drastic changes just to make sure..

Cheers!

Christian
Zhang Haixiang
User offline. Last seen 4 years 48 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
do leveling after reschedule
Paul Harris
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 11 Apr 2001
Posts: 618
If you wish the schedule to remain levelled then you should not reschedule it.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting