Resource leveling

3 replies [Last post]
Achim Kempf
User offline. Last seen 8 years 25 weeks ago. Offline
Joined: 24 Nov 2004
Posts: 4
During Precommissioning one team has to do loop checks in 20 commissioning systems, which are partly related to each other. The systems contain 1 up to 250 loops. The team is able to handle 40 loops a day. How can I manage P3 to calculate the early start of the loopchecking per systemn respec. the sequence of the systems to be checked?

Regards Achim

Replies

Philip Jonker
User offline. Last seen 15 years 23 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi achim,

Forgotten me
Achim Kempf
User offline. Last seen 8 years 25 weeks ago. Offline
Joined: 24 Nov 2004
Posts: 4
Thanks Jaco it worked. Regards from Munich Achim
Jaco Stadler
User offline. Last seen 17 years 30 weeks ago. Offline
Joined: 9 Sep 2004
Posts: 299
Groups: None
Hi Achim

I WOuld Suggest you go to the Following Method.

1) Open a P3 Schedule (in Hours)
2) Create the 20 Systems as Activity
3) Calcultate the activity Durations

Example assume System has 80 loops and you said 40 loops a Day (Assume 8 working hours) This mean activty duration is 16 hrs

Do the system Inter Logic

Assign a Resource "Loops" BQ (Number of loops / Systems)

Press level (Assign the resource Loops) Make Normal & Max lvl 5 (40 loops /8 Hours)