LEVELLING OF RESOURCE

4 replies [Last post]
Bhuvaneswaran Vel...
User offline. Last seen 5 years 48 weeks ago. Offline
Joined: 28 May 2003
Posts: 19
Groups: None
Any expert can you explain me how to convert the level dates (AFTER LEVELLING THE RESOURCE) into constrained date in P3? or Is it possible to fix the levelled dates even after scheduling (F9) in P3?

Replies

Jorge Taguinod
User offline. Last seen 2 years 19 weeks ago. Offline
Joined: 8 Jul 2003
Posts: 139
You can run a Global Change to automatically constrain the leveled early start dates:

Create a new Global Change statement and in the Then area, write:

SNE EQ ES

This should work.

regards,

Jorge Taguinod
Bhuvaneswaran Vel...
User offline. Last seen 5 years 48 weeks ago. Offline
Joined: 28 May 2003
Posts: 19
Groups: None
THXS A LOT.
Martin Polack
User offline. Last seen 20 years 23 weeks ago. Offline
Joined: 19 Jul 2001
Posts: 3
Groups: None
...or maybe you may make a copy of the "resource levelled" scheduled and use it as a Target 1 (or 2). Then you can prepare a layout comparing that Target against your current schedule.
Steven Oliver
User offline. Last seen 11 years 22 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Try creating a custom data item to hold the levelled value of early start, and after re-scheduling set the early start constraint equal to the custom data item