Resource Leveling Need Help

2 replies [Last post]
Michael Craig
User offline. Last seen 17 years 7 weeks ago. Offline
Joined: 9 Mar 2006
Posts: 5
Groups: None
I need to maintain the Resource Leveled dates and I want to know what to expect when I resource level and turn off the option to ’Preserve scheduled early and late dates". Please in you have any information on this I would greatly appreciate it if you could post it back to me.

No one in my dept knows much about resource leveling!!!

Thanks
Michael

Replies

Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
P3ec has two places where dates can go, early dates and planned dates. When you perform a CPM analysis, the calculations go into the early dates section. When you do a resource leveling, the new leveled dates go into the planned dates section. The leveled dates will also go into the early dates section unless you use the option that you asked about. Good luck!
Michael Craig
User offline. Last seen 17 years 7 weeks ago. Offline
Joined: 9 Mar 2006
Posts: 5
Groups: None
I should have clarified sorry I’m talking about P3E 4.0

Thanks