PROJECTS WITH HOURLY TIMESCALE

5 replies [Last post]
Kris Harry
User offline. Last seen 13 years 43 weeks ago. Offline
Joined: 4 Oct 2004
Posts: 47
Groups: None
Hi,

I want to know how I get started on projects where hour is the time unit. How do I define calendars etc.

Replies

Kris Harry
User offline. Last seen 13 years 43 weeks ago. Offline
Joined: 4 Oct 2004
Posts: 47
Groups: None
Thanks guys I’ll try it

Kris
Daniel Limson
User offline. Last seen 5 years 48 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None
Thanks Philip, You are right! I did not know that feature is available nowadays.

Regards,
Daniel
Philip Jonker
User offline. Last seen 16 years 29 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
P3 can schedule in hours. When you start a new project, select hours next to planning unit.
Daniel Limson
User offline. Last seen 5 years 48 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None
There is a P3 version called "Finest Hour", This software allows you to schedule in Hours. I dont know if it is still available in the market. We used this software when it was still in DOS version. You can always inquire with Primavera.

Regards,
Daniel
Andrew Podolny
User offline. Last seen 1 year 49 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 130
Hi, Kris.
It’s not too much difference when you’re working with hour based calendar. You’ll find an extra scale in calendar definition form - hours. Of course now you’ll deal with working time for each day. By default P3 assumes that each working day is starting at 12:00 AM and ending at 11:59 PM. So you’ve to change this extra night shift standard calendar according to you scenario.
Best regards,
Andrew