Raj Maurya
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 17 Jul 2004
Posts: 132
Can any one tell how to show milestone symbol in legend block of P3?

Replies

Rafael Davila
User offline. Last seen 3 hours 41 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229
Be careful with Suretrak and P3, although my preferred combination, you must realize they are not 100% equal in their calculations: noteworthy resource constraining calculations and resulting early dates, also activity splitting among others.
As a general rule what you schedule under Suretrak will be shown equal under P3 but not necessarily the converse.

Samantha McCulloch
User offline. Last seen 7 years 20 weeks ago. Offline
Joined: 5 Sep 2003
Posts: 10
Try:

Format>Bar
Pattern, Select "Pattern bars based on Act code", "Milestone".

Create a Code Value/Pettern and Pattern Colour for each milestone you would like to see in your ledgend. Then select "Ledgend". This will create an output file using your P3 file location and project name.WMF.

Then in your Footer select Logo in one of your option boxes, then "browse" and select the file you just created.

I hope this helps

Samantha
Brennan Westworth
User offline. Last seen 6 years 51 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
Ive never noticed that Milestones don’t show up in P3’s bar chart legend :|

The only way to do it is to create an image file and insert it as a logo as the previous post pointed out.

Alternately Print your schedule reports from Suretrak, The bar chart legend in suretrak includes start and finish milestones.
Raj Maurya
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 17 Jul 2004
Posts: 132
Moises,
The steps you wrote that applies to all activity. And other thing is that for doing that I have to create Target first which I don’t want. Is there any else method to show milestone or modified milestone symbols to place with legends of other bar. I can draw and insert the symmbol in bar area is one option.
Forum Guest
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
Donato, wouldn’t that make all your activities become milestones.

Please have another look and let me know.

Zq qz
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Steps :
1-     format >> bars
2-     Add >> Milestone ( bar name)
3-     Modify : Start Point – Target 1or 2 early start - make show box to “blank”
4-     Modify : Finish Point – Target 1or 2 early start - make show box to “tick”
5-     Modify : bar make outline “Blank”
6-     Make Bar color – “white”

hope this help
Forum Guest
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
Create any legend you want in bitmap or metafile format and attach it to your footer as a logo.

Hope this will help.

proj_planner